Location
105 Beddington Lane, Croydon, Surray, CR0 4TD
Duration
From 18.06.2018 - Till 25.03.2019
Contractor
Lagan Group, Barrier Architeсtural
Works accomplished
Project- Energy Recovery Facility - Beddington Croydon. REBUILD Zinc panels system 5000m2 - including (liners panels, bars with brackets, insulation, plywood, membrane and zinc panels) ...VEIO panels system 5000m2 - including (liners panels, bars with brackets, insulation, VEIO panels) ......Aluminium MESH panels 1000m2 - (with brackets fixed to still) .... Aluminium Copings 900L/m.......Aluminium Flashings and corners 700 L/m....Sandwich panels (2000m2)
Workers involved
20 cladders